City of Hamburg, District Heating Tivoli
Construction of a district heating system
- 560 m construction of plastic-coated twin-pipes diameter 200 mm
- construction of pipe trench shoring out of wooden planks 1,800 m²
and horizontal timber sheeting 300 m² - construction of foot bridges and road bridges
- removal and new installation of road drainage
- pick up and rebuilding of all surfaces:
kerbs, flagstones, concrete paving, asphalt, base courses - Road construction:
Bk 3.2 approximately 80 m²
Bk 100 approximately 465 m²
Length: 560 m
Depth: 1.60 m
Order details
Customer:
HanseWerk Natur GmbH
Period of implementation:
10/2016-
07/2017
Order volume:
770.2 k euro net