Neumünster, B-Plan 177 "Rendsburger Strasse"

Diversion of flow

  • groundwater lowering: 
    20 m circumferential collector pipe, induction of filters, 80 m outlet pipe, vaccum pump
  • construction of 2 deep wells by drilling in a depth of 12 m and submersible pumps with a capcity of 50 - 90 m³/h
  • placement of a pump shaft
  • open dewatering 

 

Depth: up to 12 m

Order details

Customer:
Granit Tiefbau GmbH

Period of implementation:
11/2014- 12/2014

Order volume:
28.5 k euro net