Hamburg, Anckelmannsplatz
Civil engineering work
- New laying of 220 m KMR DN 600/700 and 180 m DN 200/250
- Construction of 90 m pipe trench with sealing piles W 2.50 x D 3.0 m and 100 m pipe trench with soldier pile wall shoring W 4.35 x D 3.50 m
- Construction of an excavation pit with soldier pile wall shoring L 12 x W 9 x D 2
Execution details
- Client
- Hamburger Energiewerke GmbH
- Execution period
- 03/2024 – 07/2024
- Execution volume
- 3.36 million euros net