Hamburg, Anckelmannsplatz

Construction of a water supply line

  • 8 m DN 200 St C PE
  • 17 m DN 300 St C PE
  • 6 m DN 600 St C PE
  • 325 m DN 800 St C PE
  • installing ob 150 m St C PE DN 800 in existing steel pipes DN 1100 + DN 1300
  • 1,000 m² horizontal timber sheeting and strongframe method
  • installation of 4 shut-off valves, 4 slides and 2 underground hydrants
  • gattering and rebuilding of 1,25 m² asphalt and 900 m² concrete flagstones

Length: 356 m

Execution details

Client
Hamburger Wasserwerke GmbH
Execution period
08/2019 – 07/2020
Execution volume
2.32 m Euro net