Hamburg, Stockmeyerstrasse
Reconstruction of sewer
- 2 x 50 m laying of pressure pipes DN 200 PE mm under a railway bridge
- 33 m pipe jacking of a stoneware pipe DN 250
Particular challenges:
- the work was only possible at high tide
- the middle of the canal had to be cleared for shipping
- strong flow, the pontoon had to be well anchored
Length: 133 m
Depth: 2.0 m - 5.0 m
Execution details
- Client
- Hamburger Stadtentwässerung
- Execution period
- 08/2011 – 09/2011
- Execution volume
- 185 k Euro net